TMP FOR COAL-FIRED POWER PLANT FOR ASHAKACEM

The Traffic Management Plan (TMP) project was carried out in Lafarge AshakaCem Coal-Fired Power Plant (CPP), Ashaka, Gombe State as part of a 5-part Post Impact Assessment 16mw project. The CPP will generate power for the cement factory using coal as fuel.

The project commenced in November, 2017 and lasted for a period of two month. The objectives of the TMP are:

  • to improve routes of existing traffic system
  • achieve sustainable management that can provide traffic control devises
  • acquire useful information on the volume of traffic
  • classification of the vehicle size and capacity
  • the directional split to identify tidal flow on the routes, generate information that would enable effective design.

EIA FOR LAFARGEHOLCIM ASHAKACEM COAL FIRED POWER PLANT (CPP)

Ashawa Consults Ltd. were commissioned to carry out an Environmental Impact Assessment (EIA) study for Lafarge AshakaCem Coal-Powered Plant in Gombe state, 2015. The objectives for this EIA were:

  • To satisfy local, state, federal, and international rules and regulations on environmental issues relating to Energy projects.
  • Acquire Baseline data of the environment as well as the socio-economic and health conditions around the facility and host communities.
  • Identify the environmental sensitivities of the study area.
  • Assess the environmental cost and benefits of the project to the community likely to be affected by the proposed project.